Latest ASME B31.1-2022 Questions and Answers

Here you can read the most important and latest ASME B31.1-2022: Power Piping Multiple Choice Questions and Answers.

1.

Chapter I Scope and Definitions
What is the purpose of ASME B31.1-2022 – Power Piping?

 
 
 
 

2.

Which organization publishes ASME B31.1-2022?

 
 
 
 

3.

What is the scope of ASME B31.1-2022?

 
 
 
 

4.

According to ASME B31.1-2022, what does “power piping” include?

 
 
 
 

5.

Which piping systems are covered by ASME B31.1-2022?

 
 
 
 

6.

What is boiler external piping according to ASME B31.1-2022?

 
 
 
 

7.

Who is responsible for the installation of boiler external piping?

 
 
 
 

8.

What is NOT considered part of the boiler external piping?

 
 
 
 

9.

What is the purpose of ASME B31.1-2022 Appendix F?

 
 
 
 

10.

When is it necessary to specify measures beyond those required by ASME B31.1-2022?

 
 
 
 

11.

Chapter II Design:
What does ASME B31.1-2022 define as the design conditions for power piping systems?

 
 
 
 

12.

In ASME B31.1-2022, how are pressures typically expressed?

 
 
 
 

13.

What is the internal design pressure required for power piping systems in ASME B31.1-2022?

 
 
 
 

14.

When is the external design pressure considered in the design of power piping?

 
 
 
 

15.

Which of the following is not considered a source of pressure to be addressed in power piping design according to ASME B31.1-2022?

 
 
 
 

16.

What is the design temperature for steam, feedwater, and hot water piping leading from fired equipment in ASME B31.1-2022?

 
 
 
 

17.

In ASME B31.1-2022, what should be considered in selecting the design temperature for piping to be operated above 800°F (425°C)?

 
 
 
 

18.

When cooling of fluid may reduce the pressure in the piping to below atmospheric, what provision should be made according to ASME B31.1-2022?

 
 
 
 

19.

How should exposed piping be designed to withstand wind loadings according to ASME B31.1-2022?

 
 
 
 

20.

Which code can be used as an alternate method of seismic qualification or for guidance in seismic design in ASME B31.1-2022?

 
 
 
 

21.

How should piping be arranged and supported in consideration of vibration according to ASME B31.1-2022?

 
 
 
 

22.

Chapter III Materials
Which materials are considered “listed and acceptable” according to ASME B31.1-2022?

 
 
 
 

23.

When can materials not listed in Appendix A be considered acceptable according to ASME B31.1-2022?

 
 
 
 

24.

What are the temperature limits for materials listed in the Allowable Stress Tables in Mandatory Appendix A of ASME B31.1-2022?

 
 
 
 

25.

What is the purpose of the hardness testing for materials like ASTM A217, Grade C12A, and ASTM A1091, Grade C91 castings according to ASME B31.1-2022?

 
 
 
 

26.

When performing weld repairs on materials conforming to ASTM A217, Grade C12A, which welding processes and consumables are acceptable according to ASME B31.1-2022?

 
 
 
 

27.

What action should be taken if any portion of a component is heated to a temperature greater than 1,470°F (800°C) during manufacturing, according to ASME B31.1-2022?

 
 
 
 

28.

What materials may be used for water and other nontoxic, nonflammable service in ductile iron components conforming to ANSI/AWWA standards according to ASME B31.1-2022?

 
 
 
 

29.

What is the primary concern when using nonferrous metals in piping systems, as per ASME B31.1-2022?

 
 
 
 

30.

Which of the following materials may be used for pipe-supporting elements according to ASME B31.1-2022?

 
 
 
 

31.

When can malleable iron be used in piping systems, according to ASME B31.1-2022?

 
 
 
 

32.

What is the upper-temperature limit for materials listed in the Allowable Stress Tables in Mandatory Appendix A of ASME B31.1-2022?

 
 
 
 

33.

Chapter IV Reference Specifications, Codes, and Standards
Which ASME standard is referred to for the design of unified inch screw threads?

 
 
 
 

34.

What is the purpose of ASME B16.5?

 
 
 
 

35.

Which ASME standard provides guidelines for the prevention of water damage to steam turbines used for electric power generation in fossil-fueled plants?

 
 
 
 

36.

What material specification covers flat products made of steel for pressure purposes with specified elevated temperature properties?

 
 
 
 

37.

Which ASTM standard provides specifications for seamless carbon steel boiler tubes for high-pressure service?

 
 
 
 

38.

What does ASNT CP-189 stand for?

 
 
 
 

39.

Which AWS standard defines recommended practices for local heating of welds in piping and tubing?

 
 
 
 

40.

What is the purpose of AWWA C150/A21.50?

 
 
 
 

41.

Which MSS standard specifies the standard finishes for contact faces of pipe flanges and connecting-end flanges of valves and fittings?

 
 
 
 

42.

What is the primary purpose of ASME B31.1-2022?

 
 
 
 

43.

Which ASTM standard provides specifications for stainless steel bars and shapes?

 
 
 
 

44.

What ASME standard is referenced for the quality standard for steel castings and forgings for valves, flanges, and fittings, including the magnetic particle examination method?

 
 
 
 

45.

Which AWS standard defines welding terms and definitions?

 
 
 
 

46.

What is the purpose of NFPA 85?

 
 
 
 

47.

Chapter V Fabrication, Assembly, and Erection
Which chapter of ASME B31.1-2022 primarily covers the fabrication, assembly, and erection of power piping?

 
 
 
 

48.

What are the requirements for welding processes under ASME B31.1-2022?

 
 
 
 

49.

What materials should welding electrodes and filler metals conform to under ASME B31.1-2022?

 
 
 
 

50.

Which of the following is NOT a requirement for welding electrodes and filler metals used in power piping?

 
 
 
 

51.

What is the maximum allowable sulfur content for ferrous metal backing rings that become a permanent part of the weld?

 
 
 
 

52.

When austenitic steels are joined to ferritic steels, what structure should the weld metal have?

 
 
 
 

53.

What is the minimum alignment tolerance for the inside diameters of piping components to be butt-welded?

 
 
 
 

54.

Which type of weld is limited to a maximum concavity of 1/32 in. (0.8 mm) below the outside surface of the pipe?

 
 
 
 

55.

What is the maximum allowable undercut on the surface of girth butt welds?

 
 
 
 

56.

What is the primary purpose of a vent hole in reinforcement rings or saddles used in branch connections?

 
 
 
 

57.

When are preheat and post-weld heat treatments required for welds under ASME B31.1-2022?

 
 
 
 

58.

Who is responsible for the qualification of welding procedures under ASME B31.1-2022?

 
 
 
 

59.

What is the primary purpose of Welder/Welding Operator Performance Qualification (WPQ)?

 
 
 
 

60.

What is the maximum allowable deviation from the specified temperature during post-weld heat treatment?

 
 
 
 

61.

Chapter VI Inspection, Examination, and Testing
Who is responsible for inspection according to ASME B31.1-2022?

 
 
 
 

62.

What is the primary purpose of inspection according to ASME B31.1-2022?

 
 
 
 

63.

What qualifications must the owner’s inspector meet according to ASME B31.1-2022?

 
 
 
 

64.

When is visual examination required for welds according to ASME B31.1-2022?

 
 
 
 

65.

What type of examination is required for pressure welds operating at temperatures over 750°F (400°C)?

 
 
 
 

66.

Which nondestructive examination method is used to detect surface cracks?

 
 
 
 

67.

When is a radiographic examination required for branch connections in ASME B31.1-2022?

 
 
 
 

68.

What acceptance standards apply for welds in ASME B31.1-2022?

 
 
 
 

69.

What examination method is used to detect undercutting on the surface of longitudinal butt welds?

 
 
 
 

70.

Which examination method is primarily used for welds requiring post-weld heat treatment?

 
 
 
 

71.

When is ultrasonic examination (UT) required for welds in ASME B31.1-2022?

 
 
 
 

72.

What type of indication in radiography is unacceptable for welds?

 
 
 
 

73.

What examination method is used to evaluate root concavity in radiographic examination?

 
 
 
 

74.

Which examination method is used to evaluate the surface condition of welds before and after cleaning between passes during welding?

 
 
 
 

75.

Chapter VII Operation and Maintenance
What is the primary concern in the design, operation, and maintenance of power piping?

 
 
 
 

76.

Which entity is responsible for the safe operation and maintenance of power piping?

 
 
 
 

77.

What is the primary purpose of written operation and maintenance procedures for covered piping systems (CPS)?

 
 
 
 

78.

What aspects should be covered by operation and maintenance procedures for CPS?

 
 
 
 

79.

How should condition assessments of covered piping systems (CPS) be performed?

 
 
 
 

80.

What type of records should be maintained for covered piping systems (CPS)?

 
 
 
 

81.

What is the responsibility of personnel regarding maintenance programs?

 
 
 
 

82.

Who should perform preheat and postheat treatment operations for welding in power piping?

 
 
 
 

83.

What should the owner do if repairs to covered piping systems (CPS) are necessary?

 
 
 
 

84.

What is the purpose of CPS walkdowns?

 
 
 
 

85.

What is the primary material degradation mechanism addressed in ASME B31.1-2022?

 
 
 
 

86.

What is the specified minimum yield strength for the A335 P5c material?

 
 
 
 

87.

According to Table A-2, what is the temperature range for A369 FP2 material?

 
 
 
 

88.

What type of material is A369 FP21?

 
 
 
 

89.

What is the specified minimum tensile strength for A335 P11 material?

 
 
 
 

90.

Which type of material is listed as “1 1/4Cr–1/2Mo” in Table A-2?

 
 
 
 

Question 1 of 90

Are you Looking for the Latest ASME B31.1-2022 Questions and Answers?

Latest ASME B31.1-2022 Questions and Answers
Latest ASME B31.1-2022 Questions and Answers

With this simple-to-grab resource, you may read the most recent ASME B31.1-2022 Exam Questions and Answers designed for Power Piping. Continually update your knowledge of new developments in the industry and broaden your understanding of power pipe components and installation techniques. You may efficiently study for the ASME B31.1-2022 exam with the help of this thorough guide, which provides a user-friendly approach. These question-and-answer collections, whether you’re a novice or a seasoned professional, will offer insightful information and increase your self-assurance. Start your studies right away to pass the ASME B31.1-2022 exam and succeed in your position as power piping.

Please be aware that the PDF version of the ASME B31.1-2022 Power Piping Exam Questions and Answers is not distributed for free. You must pay if you want them. We’ll email you the Study Material Question Bank in PDF format as soon as you make payment. Download it to prepare for the ASME B31.1 test. Below is information on how to purchase the Questions Bank, a paid study resource. If you enjoy using our free ASME B31.1 Power Piping Exam Questions and Answers, you might also consider purchasing the premium study guides.

If you’re interested in taking a free ASME B31.1 – Power Piping Exam Practice Test with the latest questions and answers, simply click here: ASME B31.1 Exam Practice Test. It’s a great time and opportunity to practice and test your knowledge. Enjoy!

If You Want to Buy the Latest ASME B31.1 -2022 Exam Self Study Material, Please Feel Free to contact us.
Buy the Latest ASME B31.1 Exam Study Material Questions Bank
FOR EVERY 10 QUESTIONS 1 QUESTION COMES INTO THE EXAM
WE HAVE THE LATEST ASME B31.1– POWER PIPING EXAM QUESTION BANK
Total 800+ nos Questions with Answers
Cost: $25
Email Us To Buy: upweld.org@gmail.com
Click Here To Contact us On WhatsApp https://wa.link/4dn6ee
Get Printable Formats Instant download.

Take A Free ASME Exam Practice Test
Latest ASME B 31.3 Question and Answers Latest ASME B16.5 Question and Answers
Latest ASME Section V Question and Answers Latest ASME Section IX Question and Answers
Latest ASME PCC-2 Question and Answers Latest ASME BPVC Section VIII, Div 1 Question and Answers

If you want to get ASME B31.1 2022 – Power Piping Training and Certification, Please feel free to contact us. 

Leave a Reply